The Bluecoat School

Project Duration: 2 weeks

The Chapel Block at The Bluecoat School in Edgbaston had recently had its 29year old Hoval boiler condemned and the block was without heating. Midland HVAC undertook the project at short notice with a complete turn around in 2 weeks.

The old boiler, pipework and electrical supplies were removed and disposed of, the boiler room walls and floor were painted and 2 new Remeha Quinta Ace boilers were installed along with new pipework, Grundfos Magna1 pumpset, Mikrofill pressurization sets and a plate heat exchanger to seperate the boiler circuit from the existing system.

Get in Touch

Talk to the team about your project.

Office

The Oakley, Kidderminster Road
Droitwich
WR9 9AY

Contact

01562 822514
office@midlandhvac.co.uk